Accomplishments

Downtown Line 902 Promenade Station

Project No.42
Project NameDowntown Line 902 Promenade Station
AliasC902
Construction TypeDiaphragm Wall
Year2009
Construction Period2009.02 - 2010.04
StatusCompleted Project
CountrySingapore
ClientLTA
Main ContractorShanghai Tunnel
Scope of Works

D-wall (D/W=549m, T=0.8~1.5m)-24,915m3.
D-wall (Low Head Room)
(G/W=91m, H=40m, T=1.0m)-2,518m3.
Launch Shaft D-wall – (G/W=168m, T=1.0~1.5m) – 10,562m3.

AddressRaffles Blvd, Singapore