Accomplishments

East-West Transmission Cable Tunnel Project EW1

Project No.60
Project NameEast-West Transmission Cable Tunnel Project EW1
AliasEW cable tunnel
Construction TypeDiaphragm Wall
Year2013
Construction Period2013.01 - 2013.10
StatusCompleted Project
CountrySingapore
ClientSP Power
Main ContractorObayashi
Scope of Works

Diaphragm Wall;
Shaft 1 – Dia=16m, H=25.5m, T=1.0m,
Shaft 2 – Dia=14m, H=39.7m, T=1.0m,
Shaft 3 – Dia=16m, H=37.5m, T=1.0m,
C&C Tunnel- G/W= 517m, H=20m, T=0.8m. Total volume = 13,659m3.

AddressAyer Rajah Crescent, Singapore