Accomplishments

Thomson Line 226 Marina South Station

Project No.62
Project NameThomson Line 226 Marina South Station
AliasT226
Construction TypeDiaphragm Wall
Year2014
Construction Period2014.04 - 2017.01
StatusCompleted Project
CountrySingapore
ClientLTA
Main ContractorTaisei
Scope of Works

D-wall (G/W=1,189m, T= 1.2~1.5m) – 96,817m3.
Barrette Piles (G/W=344, T=1.2~1.5m) – 33,444m3.
Bored piles (Φ1.0~2.0m) – 122nos.

AddressMarina Bay, Singapore